The new Pumps have had the plumbing connected and wiring has started...
Two sections of the new hand/guard rail are in place, looks like a much more robust rail system to me...
More concrete has been poured and workers are still working on laying the highlight pavers in the poured sections of the walkways...
I spoke with Larry, the site Project Manager, by phone and he indicated that starting this week work would commence on placing the new lights in the Fountain pool (all of those round concrete forms are for lighting mounting)...
Oh and the Former Modis building is now nameless...
That is about it for this report, however I am considering trying to slip some additional updates in place possibly as early as this Friday...
Until next time,
Bob